Progress Report Phase 1 -
Maths & Geography Building
The Tender documents were returned by the four chosen
contractors on 5th June and following extensive analysis
and discussion, John Jarvis Ltd has been selected
as our preferred builder.
A Letter of Intent has been submitted to John Jarvis
today, 26th June with an expected date of 28th July
for building work to begin. John Jarvis are a local
company, established in 1911, who have previously
worked at Judd as well as other schools in the area.
We are confident that the start date will enable us
to fit out the new building in August 2009 so that
it is ready for occupation in September 2009.
In addition to the regular fundraising campaign, the
Old Juddian Society launched a Buy a Brick Campaign
this month. Former students of the school are being
encouraged to purchase bricks at £50 each, with
a target of 1000 bricks being sold. Initial response
to the campaign has been encouraging with bricks being
bought by OJs who left the school as long ago as 1936!